Construction Update, February 2026

Construction Progress Hits 70%

Construction Update

The Terrace Homes at Marbella Beachside, Scarborough are continuing to make excellent progress, with noticeable advancement across the site in recent weeks.

The project has now reached approximately 70% overall completion, reflecting steady movement through key stages of construction.

Internally, fit-out works are around 60% complete, with trades actively progressing throughout the residences as finishes and detailing begin to come together.

Externally, landscaping has also reached approximately 60% completion, with the outdoor spaces continuing to develop and enhance the overall coastal aesthetic of the homes.

With each milestone achieved, the Terrace Homes are moving closer to completion, and the quality and design intent of the development is becoming increasingly evident.