Third-tier slab underway
Construction Update
Level 3 slab pour began last week (13/11) and will be completed tomorrow (21/11).
Level 3 brickwork will commence next week (estimated to be complete before Christmas).
Ground floor and Level 1 exterior structures are complete.
Additionally, the State Government has proposed lowering a large section of West Coast Highway at Scarborough Beach.
This is exciting news, as the initiative aims to ease traffic congestion. Read more here.