Construction Update, November 2024

Third-tier slab underway

Construction Update

Level 3 slab pour began last week (13/11) and will be completed tomorrow (21/11).

Level 3 brickwork will commence next week (estimated to be complete before Christmas).

Ground floor and Level 1 exterior structures are complete.

Additionally, the State Government has proposed lowering a large section of West Coast Highway at Scarborough Beach.

This is exciting news, as the initiative aims to ease traffic congestion. Read more here.

Construction is forecasted for completion early-mid 2026